ICC Home  /  Members  /  Meetings  /  Peer Support  /  Documentation  /  Projects


Agenda for 4/13/07 ICC Meeting:


10 AM - ICS Conference Room
  1. Report from the chairman
  2. Policy:
  3. Projects:
  4. PROJECT LEAD BEGUN STATUS
    Sharepoint Test Site Ben Beach Feb 2007 For evaluation of Sharepoint's utility as a collaboration and content management solution for IFAS. (Use Gatorlink credentials for access.)
    Core service redundancy via virtualization Wayne Hyde Fall 2006 In progress
    IFAS WebDAV implementation Chris Leopold Jun 2006 Awaiting documentation and release
    Vista Deployment Benjamin Beach Dec 2005 In development
    New IFAS IP Plan Chris Leopold Oct 2005 Awaiting available time/staff for completion
    Move to IF-SRV-WEB Mark Ross Oct 2005 Set for rapid completion/replacing FTP with WebDAV
    Exit processes, NMB and permission removal Dan Cromer/????? January 2006 pending workflow and automation details
    listserv confirm settings Dan Cromer/????? Dec 2005 Pending alternate implementation
    Re-enabling Windows firewall for IFAS (GPO:IF-Firewall-Windows Clients) Wayne Hyde Oct 2005 Pending IP re-numbering
    New VPN server (if-srv-isa.ad.ufl.edu) Wayne Hyde Aug 2005 lower priority issue
    services documentation Not assigned never desperately needed
  5. Operations:
  6. Other Discussion
    • Your input is welcomed...

last edited 13 April 2007 by Steve Lasley